Case study · Ground-up multifamily

805 Washington

805 Washington is a nine-story residential building in Brooklyn with two cellar levels, across from the Brooklyn Museum. Osher was lead project manager for the developer, from the trade contracts through facade, MEP and turnover.

Building9 stories + 2 cellars
LocationAcross from the Brooklyn Museum
RoleLead project manager, developer side
ScopeGround-up: structure to turnover
MarketNew York City

The challenge

A tight corner lot with occupied neighbors on two sides and a busy avenue in front, with the most complex facade on the most visible corner. Model residences and amenity areas had to be finished for sales while the envelope was still going up.

The developer carried many trade contracts and monthly payment requisitions, city inspections, and a finish package already promised to buyers.

What we did

Osher managed the trade contracts for the developer and checked every payment requisition against the schedule of values and the work on site. He ran the weekly owner, architect and contractor meetings, kept the logs and chased open questions (RFIs).

He sequenced the facade floor by floor (panels, sheathing, insulation, glazing) so interior trades kept working, and handled the city’s issues. Inside, he tracked herringbone oak floors, stone kitchens and baths and corridor lighting unit by unit against the model.

The result

The facade was completed and the finished residences turned over, with rooftop mechanical, life-safety and amenity spaces signed off. The developer had one person accountable for the contractor and the budget.

Start to finish

How it came together

  1. 805 Washington: building under scaffold netting before facade completion
    01 · Autumn 2019

    Under scaffold netting, facade work starting

  2. 805 Washington: full elevation in weather barrier before cladding
    02 · December 2019

    Envelope: weather barrier, panels going on

  3. 805 Washington: finished stepped facade with dark and stone-look panels
    03 · July 2020

    Facade complete

  4. 805 Washington: open kitchen with dark cabinetry, marble backsplash and herringbone floors
    04 · Turnover

    Finished residences handed over

Payments follow progress

Each requisition was checked against work in place before it was paid.

The facade sets the schedule

Floor-by-floor envelope work kept interior trades busy.

Buyers buy the model unit

Tracking finishes unit by unit kept every residence to the model standard.

On site

Project gallery

Photos from the job, taken during construction. Tap any image to enlarge.

Start a project

Planning a project like this?

We’ll review it with you and send a written proposal. The first consultation is free.

  • A 30-minute call with Osher about your project
  • An honest opinion, even if you decide not to hire us
  • A written proposal: flat monthly retainer or a percentage of construction value
Call or text(570) 339-7793Emailoffice@monsterprojectgroup.com
Office500 E Broward Blvd, Suite 900, Fort Lauderdale

Get your free consultation

Osher reviews every request personally. Only name, phone and email are required.

Add your name.
Add a phone number we can call.
Add a valid email.
Confidential. We never share your details.Prefer to talk? (570) 339-7793
CallFree consultation